... 24. In
preparation for this
Regulation, the
Commission has
launched REACH
Implementation Projects (RIPs), involving
relevant experts from
stakeholder groups. Some of those
projects aim at developing
draft guidelines and tools which should
help the
Commission, the
Agency,
Member States,
manufacturers,
importers and
downstream users of
substances to fulfil, in concrete
terms, their
obligations under this
Regulation. This
work should enable the
Commission and the
Agency to make available appropriate
technical guidance, in
due time, with
regard to the deadlines
introduced by this
Regulation. ...
... 24. In
preparation for this
Regulation, the
Commission has
launched REACH
Implementation Projects (RIPs), involving
relevant experts from
stakeholder groups. Some of those
projects aim at developing
draft guidelines and tools which should
help the
Commission, the
Agency,
Member States,
manufacturers,
importers and
downstream users of
substances to fulfil, in concrete
terms, their
obligations under this
Regulation. This
work should enable the
Commission and the
Agency to make available appropriate
technical guidance, in
due time, with
regard to the deadlines
introduced by this
Regulation. ...
... 44. In
order to provide a harmonised, simple
system, all registrations should be submitted to the
Agency. To ensure a consistent approach and
efficient use of
resources, it should perform a completeness check on all registrations and take
responsibility for any final rejections of registrations. ...
... 47. In
accordance with Directive 86/609/EEC, it is necessary to replace, reduce or refine
testing on
vertebrate animals.
Implementation of this
Regulation should be based on the use of alternative
test methods, suitable for the
assessment of
health and
environmental hazards of
chemicals, wherever possible. The use of
animals should be avoided by
recourse to alternative
methods validated by the
Commission or
international bodies, or recognised by the
Commission or the
Agency as appropriate to
meet the
information requirements under this
Regulation. To this end, the
Commission, following
consultation with
relevant stakeholders, should
propose to
amend the
future Commission Regulation on
test methods or this
Regulation, where appropriate, to replace, reduce or refine
animal testing. The
Commission and the
Agency should ensure that
reduction of
animal testing is a key
consideration in the
development and
maintenance of
guidance for
stakeholders and in the
Agency's own
procedures. ...
... 47. In
accordance with Directive 86/609/EEC, it is necessary to replace, reduce or refine
testing on
vertebrate animals.
Implementation of this
Regulation should be based on the use of alternative
test methods, suitable for the
assessment of
health and
environmental hazards of
chemicals, wherever possible. The use of
animals should be avoided by
recourse to alternative
methods validated by the
Commission or
international bodies, or recognised by the
Commission or the
Agency as appropriate to
meet the
information requirements under this
Regulation. To this end, the
Commission, following
consultation with
relevant stakeholders, should
propose to
amend the
future Commission Regulation on
test methods or this
Regulation, where appropriate, to replace, reduce or refine
animal testing. The
Commission and the
Agency should ensure that
reduction of
animal testing is a key
consideration in the
development and
maintenance of
guidance for
stakeholders and in the
Agency's own
procedures. ...
... 47. In
accordance with Directive 86/609/EEC, it is necessary to replace, reduce or refine
testing on
vertebrate animals.
Implementation of this
Regulation should be based on the use of alternative
test methods, suitable for the
assessment of
health and
environmental hazards of
chemicals, wherever possible. The use of
animals should be avoided by
recourse to alternative
methods validated by the
Commission or
international bodies, or recognised by the
Commission or the
Agency as appropriate to
meet the
information requirements under this
Regulation. To this end, the
Commission, following
consultation with
relevant stakeholders, should
propose to
amend the
future Commission Regulation on
test methods or this
Regulation, where appropriate, to replace, reduce or refine
animal testing. The
Commission and the
Agency should ensure that
reduction of
animal testing is a key
consideration in the
development and
maintenance of
guidance for
stakeholders and in the
Agency's own
procedures. ...
... 99. The
Agency should have the means to perform all the tasks required to carry out its
role. ...
... Any
manufacturer,
importer, or where
relevant downstream user, may, whilst retaining
full responsibility for complying with his
obligations under this
Regulation, appoint a
third party representative for all
proceedings under
Article 11,
Article 19, Title III and
Article 53 involving
discussions with other
manufacturers,
importers, or where
relevant downstream users. In these
cases, the
identity of a
manufacturer or
importer or
downstream user who has appointed a
representative shall not normally be disclosed by the
Agency to other
manufacturers,
importers, or, where
relevant,
downstream users. ...
ARTICLE-6: General obligation to register substances on their own or in preparations [
go to this ARTICLE]
ARTICLE-7: Registration and notification of substances in articles [
go to this ARTICLE]
... (b) the Agency has grounds for suspecting that: ...
ARTICLE-9: Exemption from the general obligation to register for product and process orientated research and development (PPORD) [
go to this ARTICLE]
ARTICLE-12: Information to be submitted depending on tonnage [
go to this ARTICLE]
ARTICLE-13: General requirements for generation of information on intrinsic properties of substances [
go to this ARTICLE]
ARTICLE-16: Duties of the Commission, the Agency and registrants of substances regarded as being registered [
go to this ARTICLE]
ARTICLE-17: Registration of on-site isolated intermediates [
go to this ARTICLE]
ARTICLE-18: Registration of transported isolated intermediates [
go to this ARTICLE]
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
... 2. The
Agency shall
undertake a completeness check of each
registration in
order to ascertain that all the elements required under
Articles 10 and
12 or under
Articles 17 or
18, as well as the
registration fee referred to in
Article 6(4),
Article 7(1) and (5),
Article 17(2) or
Article 18(2), have been provided. The completeness check shall not
include an
assessment of the
quality or the adequacy of any
data or justifications submitted. The
Agency shall
undertake the completeness check within three
weeks of the submission
date, or within three
months of the
relevant deadline of
Article 23, as
regards registrations of
phase-in substances submitted in the course of the two-
month period immediately preceding that deadline. If a
registration is incomplete, the
Agency shall inform the
registrant, before
expiry of the three-
week or three-
month period referred to in the second subparagraph, as to what further
information is required in
order for the
registration to be complete, while setting a
reasonable deadline for this. The
registrant shall complete his
registration and submit it to the
Agency within the deadline set. The
Agency shall confirm the submission
date of the further
information to the
registrant. The
Agency shall perform a further completeness check, considering the further
information submitted. The
Agency shall
reject the
registration if the
registrant fails to complete his
registration within the deadline set. The
registration fee shall not be reimbursed in such
cases. ...
ARTICLE-21: Manufacturing and import of substances [
go to this ARTICLE]
... 1. A
registrant may start or
continue the
manufacture or
import of a
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date, without
prejudice to
Article 27(8). In the
case of registrations of
phase-in substances, such a
registrant may
continue the
manufacture or
import of the
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date or, if submitted within the two-
month period before the
relevant deadline of
Article 23, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
months from that deadline, without
prejudice to
Article 27(8). In the
case of an update of a
registration according to
Article 22 a
registrant may
continue the
manufacture or
import of the
substance, or the
production or
import of the
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the update
date, without
prejudice to
Article 27(8). ...
... 1. A
registrant may start or
continue the
manufacture or
import of a
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date, without
prejudice to
Article 27(8). In the
case of registrations of
phase-in substances, such a
registrant may
continue the
manufacture or
import of the
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date or, if submitted within the two-
month period before the
relevant deadline of
Article 23, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
months from that deadline, without
prejudice to
Article 27(8). In the
case of an update of a
registration according to
Article 22 a
registrant may
continue the
manufacture or
import of the
substance, or the
production or
import of the
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the update
date, without
prejudice to
Article 27(8). ...
... 1. A
registrant may start or
continue the
manufacture or
import of a
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date, without
prejudice to
Article 27(8). In the
case of registrations of
phase-in substances, such a
registrant may
continue the
manufacture or
import of the
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date or, if submitted within the two-
month period before the
relevant deadline of
Article 23, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
months from that deadline, without
prejudice to
Article 27(8). In the
case of an update of a
registration according to
Article 22 a
registrant may
continue the
manufacture or
import of the
substance, or the
production or
import of the
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the update
date, without
prejudice to
Article 27(8). ...
... 1. A
registrant may start or
continue the
manufacture or
import of a
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date, without
prejudice to
Article 27(8). In the
case of registrations of
phase-in substances, such a
registrant may
continue the
manufacture or
import of the
substance or
production or
import of an
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the submission
date or, if submitted within the two-
month period before the
relevant deadline of
Article 23, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
months from that deadline, without
prejudice to
Article 27(8). In the
case of an update of a
registration according to
Article 22 a
registrant may
continue the
manufacture or
import of the
substance, or the
production or
import of the
article, if there is no indication to the
contrary from the
Agency in
accordance with
Article 20(2) within the three
weeks after the update
date, without
prejudice to
Article 27(8). ...
ARTICLE-22: Further duties of registrants [
go to this ARTICLE]
ARTICLE-26: Duty to inquire prior to registration [
go to this ARTICLE]
ARTICLE-27: Sharing of existing data in the case of registered substances [
go to this ARTICLE]
ARTICLE-28: Duty to pre-register for phase-in substances [
go to this ARTICLE]
ARTICLE-29: Substance Information Exchange Fora [
go to this ARTICLE]
ARTICLE-30: Sharing of data involving tests [
go to this ARTICLE]
ARTICLE-36: Obligation to keep information [
go to this ARTICLE]
ARTICLE-37: Downstream user chemical safety assessments and duty to identify, apply and recommend risk reduction measures [
go to this ARTICLE]
... 3. For
registered substances, the
manufacturer,
importer or
downstream user shall comply with the
obligations laid down in
Article 14 either before he next
supplies the
substance on its own or in a
preparation to the
downstream user making the
request referred to in paragraph 2 of this
Article, provided that the
request was made at least one
month before the
supply, or within one
month after the
request, whichever is the later. For
phase-in substances, the
manufacturer,
importer or
downstream user shall comply with this
request and with the
obligations laid down in
Article 14 before the
relevant deadline in
Article 23 has expired, provided that the
downstream user makes his
request at least 12
months before the deadline in
question. Where the
manufacturer,
importer or
downstream user, having assessed the use in
accordance with
Article 14, is
unable to
include it as an
identified use for
reasons of
protection of
human health or the
environment, he shall provide the
Agency and the
downstream user with the
reason(s) for that
decision in
writing without
delay and shall not
supply downstream user(s) with the
substance without
including these
reason(s) in the
information referred to under
Articles 31 or
32. The
manufacturer or
importer shall
include this use in section 3.7 of Annex VI in his update of the
registration in
accordance with
Article 22(1)(d). ...
ARTICLE-38: Obligation for downstream users to report information [
go to this ARTICLE]
ARTICLE-40: Examination of testing proposals [
go to this ARTICLE]
ARTICLE-41: Compliance check of registrations [
go to this ARTICLE]
ARTICLE-42: Check of information submitted and follow-up to dossier evaluation [
go to this ARTICLE]
ARTICLE-43: Procedure and time periods for examination of testing proposals [
go to this ARTICLE]
ARTICLE-44: Criteria for substance evaluation [
go to this ARTICLE]
... 3. In
cases where two or more
Member States have expressed an
interest in evaluating the same
substance and they cannot
agree who should be the
competent authority, the
competent authority for the
purposes of
Articles 46,
47 and
48 shall be
determined in
accordance with the following
procedure. The
Agency shall refer the matter to the
Member State Committee, in
order to
agree which
authority shall be the
competent authority, taking into
account the
Member State in which the
manufacturer(s) or
importer(s) is located, the respective proportions of total
Community gross domestic product, the
number of
substances already being evaluated by a
Member State and the
expertise available. If, within 60
days of the
referral, the
Member State Committee reaches
unanimous agreement, the
Member States concerned shall
adopt substances for
evaluation accordingly. If the
Member State Committee fails to reach a
unanimous agreement, the
Agency shall submit the conflicting
opinions to the
Commission, which shall
decide which
authority shall be the
competent authority, in
accordance with the
procedure referred to in
Article 133(3), and the
Member States concerned shall
adopt substances for
evaluation accordingly. ...
... 3. In
cases where two or more
Member States have expressed an
interest in evaluating the same
substance and they cannot
agree who should be the
competent authority, the
competent authority for the
purposes of
Articles 46,
47 and
48 shall be
determined in
accordance with the following
procedure. The
Agency shall refer the matter to the
Member State Committee, in
order to
agree which
authority shall be the
competent authority, taking into
account the
Member State in which the
manufacturer(s) or
importer(s) is located, the respective proportions of total
Community gross domestic product, the
number of
substances already being evaluated by a
Member State and the
expertise available. If, within 60
days of the
referral, the
Member State Committee reaches
unanimous agreement, the
Member States concerned shall
adopt substances for
evaluation accordingly. If the
Member State Committee fails to reach a
unanimous agreement, the
Agency shall submit the conflicting
opinions to the
Commission, which shall
decide which
authority shall be the
competent authority, in
accordance with the
procedure referred to in
Article 133(3), and the
Member States concerned shall
adopt substances for
evaluation accordingly. ...
ARTICLE-46: Requests for further information and check of information submitted [
go to this ARTICLE]
ARTICLE-47: Coherence with other activities [
go to this ARTICLE]
ARTICLE-48: Follow-up to substance evaluation [
go to this ARTICLE]
ARTICLE-49: Further information on on-site isolated intermediates [
go to this ARTICLE]
ARTICLE-50: Registrants' and downstream users' rights [
go to this ARTICLE]
ARTICLE-51: Adoption of decisions under dossier evaluation [
go to this ARTICLE]
... 3. If the
Agency does not
receive any
proposals, it shall take the
decision in the version notified under paragraph 1. ...
ARTICLE-52: Adoption of decisions under substance evaluation [
go to this ARTICLE]
ARTICLE-53: Cost sharing for tests without an agreement between registrants and/or downstream users [
go to this ARTICLE]
ARTICLE-54: Publication of information on evaluation [
go to this ARTICLE]
ARTICLE-58: Inclusion of substances in Annex XIV [
go to this ARTICLE]
ARTICLE-59: Identification of substances referred to in Article 57 [
go to this ARTICLE]
... 4. The
Agency shall
publish on its website a
notice that an Annex XV
dossier has been prepared for a
substance. The
Agency shall invite all interested
parties to submit comments within a specified deadline to the
Agency. ...
... 4. The
Agency shall
publish on its website a
notice that an Annex XV
dossier has been prepared for a
substance. The
Agency shall invite all interested
parties to submit comments within a specified deadline to the
Agency. ...
... 4. The
Agency shall
publish on its website a
notice that an Annex XV
dossier has been prepared for a
substance. The
Agency shall invite all interested
parties to submit comments within a specified deadline to the
Agency. ...
... 10. The
Agency shall
publish and update the
list referred to in paragraph 1 on its website without
delay after a
decision on inclusion of a
substance has been taken. ...
ARTICLE-62: Applications for authorisations [
go to this ARTICLE]
... 1. An
application for an authorisation shall be made to the
Agency. ...
ARTICLE-64: Procedure for authorisation decisions [
go to this ARTICLE]
ARTICLE-69: Preparation of a proposal [
go to this ARTICLE]
... 4. If a
Member State considers that the
manufacture, placing on the
market or use of a
substance on its own, in a
preparation or in an
article poses a
risk to
human health or the
environment that is not adequately controlled and needs to be addressed it shall notify the
Agency that it
proposes to prepare a
dossier which conforms to the
requirements of the
relevant sections of Annex XV. If the
substance is not on the
list maintained by the
Agency referred to in paragraph 5 of this
Article, the
Member State shall prepare a
dossier which conforms to the
requirements of Annex XV within 12
months of the
notification to the
Agency. If this
dossier demonstrates that
action on a
Community-
wide basis is necessary, beyond any
measures already in
place, the
Member State shall submit it to the
Agency in the format outlined in Annex XV, in
order to initiate the
restrictions process. The
Agency or
Member States shall refer to any
dossier,
chemical safety report or
risk assessment submitted to the
Agency or
Member State under this
Regulation. The
Agency or
Member States shall also refer to any
relevant risk assessment submitted for the
purposes of other
Community Regulations or Directives. To this end other
bodies, such as
agencies,
established under
Community law and carrying out a similar task shall provide
information to the
Agency or
Member State concerned on
request. The
Committee for
Risk Assessment and the
Committee for
Socio-economic Analysis shall check whether the
dossier submitted conforms to the
requirements of Annex XV. Within 30
days of
receipt, the respective
Committee shall inform the
Agency or the