ARTICLE-9: Exemption from the general obligation to register for product and process orientated research and development (PPORD)     [go to this ARTICLE]
... 5. In the absence of any indication to the contrary, the manufacturer or importer of the substance or the producer or importer of articles may manufacture or import the substance or produce or import the articles not earlier than two weeks after the notification. ...


ARTICLE-20: Duties of the Agency     [go to this ARTICLE]
... 2. The Agency shall undertake a completeness check of each registration in order to ascertain that all the elements required under Articles 10 and 12 or under Articles 17 or 18, as well as the registration fee referred to in Article 6(4), Article 7(1) and (5), Article 17(2) or Article 18(2), have been provided. The completeness check shall not include an assessment of the quality or the adequacy of any data or justifications submitted. The Agency shall undertake the completeness check within three weeks of the submission date, or within three months of the relevant deadline of Article 23, as regards registrations of phase-in substances submitted in the course of the two-month period immediately preceding that deadline. If a registration is incomplete, the Agency shall inform the registrant, before expiry of the three-week or three-month period referred to in the second subparagraph, as to what further information is required in order for the registration to be complete, while setting a reasonable deadline for this. The registrant shall complete his registration and submit it to the Agency within the deadline set. The Agency shall confirm the submission date of the further information to the registrant. The Agency shall perform a further completeness check, considering the further information submitted. The Agency shall reject the registration if the registrant fails to complete his registration within the deadline set. The registration fee shall not be reimbursed in such cases. ...
... 2. The Agency shall undertake a completeness check of each registration in order to ascertain that all the elements required under Articles 10 and 12 or under Articles 17 or 18, as well as the registration fee referred to in Article 6(4), Article 7(1) and (5), Article 17(2) or Article 18(2), have been provided. The completeness check shall not include an assessment of the quality or the adequacy of any data or justifications submitted. The Agency shall undertake the completeness check within three weeks of the submission date, or within three months of the relevant deadline of Article 23, as regards registrations of phase-in substances submitted in the course of the two-month period immediately preceding that deadline. If a registration is incomplete, the Agency shall inform the registrant, before expiry of the three-week or three-month period referred to in the second subparagraph, as to what further information is required in order for the registration to be complete, while setting a reasonable deadline for this. The registrant shall complete his registration and submit it to the Agency within the deadline set. The Agency shall confirm the submission date of the further information to the registrant. The Agency shall perform a further completeness check, considering the further information submitted. The Agency shall reject the registration if the registrant fails to complete his registration within the deadline set. The registration fee shall not be reimbursed in such cases. ...


ARTICLE-21: Manufacturing and import of substances     [go to this ARTICLE]
... 1. A registrant may start or continue the manufacture or import of a substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date, without prejudice to Article 27(8). In the case of registrations of phase-in substances, such a registrant may continue the manufacture or import of the substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date or, if submitted within the two-month period before the relevant deadline of Article 23, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three months from that deadline, without prejudice to Article 27(8). In the case of an update of a registration according to Article 22 a registrant may continue the manufacture or import of the substance, or the production or import of the article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the update date, without prejudice to Article 27(8). ...
... 1. A registrant may start or continue the manufacture or import of a substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date, without prejudice to Article 27(8). In the case of registrations of phase-in substances, such a registrant may continue the manufacture or import of the substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date or, if submitted within the two-month period before the relevant deadline of Article 23, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three months from that deadline, without prejudice to Article 27(8). In the case of an update of a registration according to Article 22 a registrant may continue the manufacture or import of the substance, or the production or import of the article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the update date, without prejudice to Article 27(8). ...
... 1. A registrant may start or continue the manufacture or import of a substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date, without prejudice to Article 27(8). In the case of registrations of phase-in substances, such a registrant may continue the manufacture or import of the substance or production or import of an article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the submission date or, if submitted within the two-month period before the relevant deadline of Article 23, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three months from that deadline, without prejudice to Article 27(8). In the case of an update of a registration according to Article 22 a registrant may continue the manufacture or import of the substance, or the production or import of the article, if there is no indication to the contrary from the Agency in accordance with Article 20(2) within the three weeks after the update date, without prejudice to Article 27(8). ...
... 2. If the Agency has informed the registrant that he is to submit further information in accordance with the third subparagraph of Article 20(2), the registrant may start the manufacture or import of a substance or production or import of an article if there is no indication to the contrary from the Agency within the three weeks after receipt by the Agency of the further information necessary to complete his registration, without prejudice to Article 27(8). ...


ARTICLE-30: Sharing of data involving tests     [go to this ARTICLE]
... 1. Before testing is carried out in order to meet the information requirements for the purposes of registration, a SIEF participant shall inquire whether a relevant study is available by communicating within his SIEF. If a relevant study involving tests on vertebrate animals is available within the SIEF, a participant of that SIEF shall request that study. If a relevant study not involving tests on vertebrate animals is available within the SIEF, a SIEF participant may request that study. Within one month of the request, the owner of the study shall provide proof of its cost to the participant(s) requesting it. The participant(s) and the owner shall make every effort to ensure that the costs of sharing the information are determined in a fair, transparent and non discriminatory way. This may be facilitated by following any cost sharing guidance which is based on those principles and is adopted by the Agency in accordance with Article 77(2)(g). If they cannot reach such an agreement, the cost shall be shared equally. The owner shall give permission to refer to the full study report for the purpose of registration within two weeks of receipt of payment. Registrants are only required to share in the costs of information that they are required to submit to satisfy their registration requirements. ...
... 2. If a relevant study involving tests is not available within the SIEF, only one study shall be conducted per information requirement within each SIEF by one of its participants acting on behalf of the others. They shall take all reasonable steps to reach an agreement within a deadline set by the Agency as to who is to carry out the test on behalf of the other participants and to submit a summary or robust study summary to the Agency. If no agreement is reached, the Agency shall specify which registrant or downstream user shall perform the test. All participants of the SIEF who require a study shall contribute to the costs for the elaboration of the study with a share corresponding to the number of participating potential registrants. Those participants that do not carry out the study themselves shall have the right to receive the full study report within two weeks following payment to the participant that carried out the study. ...


ARTICLE-96: The budget of the Agency     [go to this ARTICLE]
... 11. The Management Board shall, without delay, notify the budgetary authority of its intention to implement any project which may have significant financial implications for the funding of its budget, in particular any projects relating to property such as the rental or purchase of buildings. It shall inform the Commission thereof. Where a branch of the budgetary authority has notified its intention to deliver an opinion, it shall forward its opinion to the Management Board within a period of six weeks from the date of notification of the project. ...